Case Study — Industrial & Logistics Greenlight Milton Keynes

Project Manager, Employer’s Agent and Quantity Surveyor for a c. £20m, 176,000 sq ft industrial and logistics scheme at Precedent Drive, Milton Keynes, targeting BREEAM Outstanding, from inception through to appointing the main contractor.

The challenge

Three high-spec units built to net zero standards

Greenlight Milton Keynes industrial unit, loading doors and yard elevation

A logistics joint venture set out to deliver three new industrial and logistics units of 51,062 to 124,007 sq ft at Precedent Drive, a short walk from Milton Keynes Central. Two units were speculative and one was pre-let to an international green technology manufacturer.

The specification was demanding: BREEAM Outstanding, EPC A* and Net Zero Carbon in Operation Ready, with solar PV, EV charging, 10% rooflights, up to 15m eaves and 700 kVA of power, plus offices with balconies, breakout space and a wellness garden. All of this had to be defined, priced and secured in the contract before a contractor was appointed.

Delivered by Ollie Thompson MRICS in a previous role at Trinity Property Consultants.

Project facts

At a glance

Appointed from RIBA Stage 0 through to procuring the main contractor, on a JCT Design and Build contract with client amendments.

Client

Logistics joint venture

Location

Precedent Drive, Milton Keynes

Value

c. £20m

Contract

JCT Design and Build with client amendments

Our role

Project Manager, Employer’s Agent and Quantity Surveyor

RIBA stages

0–4, from inception to contractor appointment

Scheme

176,000 sq ft across three units: two speculative, one pre-let

Sustainability

BREEAM Outstanding, EPC A*, Net Zero Carbon in Operation Ready

Main contractor

GMI

Our approach

From inception to contractor appointment

RIBA 0

Strategic Definition

Setting the brief, budget and programme for three units, balancing speculative space with a pre-let tenant’s requirements.

BriefBudgetFeasibility
RIBA 1

Preparation & Team

Assembling the professional team and setting up project governance, reporting and cost control.

AppointmentsGovernanceCost Plan
RIBA 2

Concept Design

Testing the design against the cost plan and the BREEAM Outstanding, EPC A* and net zero targets.

DesignSustainabilityValue
RIBA 3

Spatial Coordination

Coordinating the design and keeping the budget aligned as the scheme moved through planning and the pre-let was agreed.

PlanningCoordinationCost Control
RIBA 3–4

Employer’s Requirements

Preparing the Employer’s Requirements and the client’s amendments to the JCT Design and Build contract.

ERsAmendmentsRisk
RIBA 4

Main Contractor Procurement

Running the tender, analysing the returns and appointing GMI as main contractor.

TenderAnalysisAppointment

The outcome

A net zero ready scheme, ready to build

£20m

Industrial scheme

176,000 sq ft of new industrial and logistics space.

3

Units

Two speculative units and one pre-let to a green technology manufacturer.

A*

EPC rating

With BREEAM Outstanding and Net Zero Carbon in Operation Ready.

Images: Trinity Property Consultants. See also our Greenlight Redditch case study, or our Project & Programme Management and Employer’s Agent services.

Start a Project

Tell us
about your scheme.

We’ll bring the programme, the governance and the certainty. Get in touch to discuss your project.