Case Study — Commercial Fujifilm UK HQ, Bedford

Project Manager, Quantity Surveyor and Employer’s Agent for a c. £7.5m, 30,000 sq ft headquarters combining a showroom, workshop and offices, led from first brief to handover.

The challenge

One building, three jobs to do

Reception and breakout space inside Fujifilm UK headquarters, Bedford

Fujifilm needed a new UK headquarters at Bedford Link that could do three jobs at once: a showroom for customers, a workshop for technical work, and offices for its staff. The commercial developer delivering it needed one senior adviser to lead the project and protect its cost and quality.

The 30,000 sq ft, three-storey building had to be designed and built, fitted out to Category A and handed over with its car park, landscaping and external works complete, to BREEAM Very Good and EPC A standards.

Delivered by Ollie Thompson MRICS in a previous role at Trinity Property Consultants.

Project facts

At a glance

Appointed from RIBA Stage 0 through to handover, on a design and build contract with client amendments.

Client

Commercial developer, for occupier Fujifilm

Location

Bedford Link, Bedford

Value

c. £7.5m

Contract

JCT Design and Build with client amendments

Our role

Project Manager, Quantity Surveyor and Employer’s Agent

RIBA stages

0–6, from inception to handover

Size

30,000 sq ft over three storeys

Sustainability

BREEAM Very Good, EPC A

Completed

Q3 2020, with mcs group as contractor

Our approach

From first brief to handover

RIBA 0–1

Brief & Budget

Appointed at the very start, Ollie shaped the brief and budget around Fujifilm’s mix of showroom, workshop and office space.

BriefBudgetProgramme
RIBA 2–3

Employer’s Requirements

He prepared the Employer’s Requirements, setting out exactly what the contractor needed to design and build, including the BREEAM and EPC targets.

ERsCost PlanSustainability
RIBA 4

Tender & Contract

He ran the tender and agreed the client’s amendments to the JCT Design and Build contract.

TenderAmendmentsAppointment
RIBA 5

Construction

As project manager and Employer’s Agent, he administered the contract with mcs group through a 37-week build programme.

ProgrammeAdministrationSite
RIBA 5

Cost Control

Monthly valuations and cost reports gave the client a clear forecast of the final cost, with changes assessed before being instructed.

ValuationsChangeReporting
RIBA 6

Handover

The building was handed over in Q3 2020 with its Category A fit-out, car park and landscaping complete.

CompletionHandoverFinal Account

The outcome

A sustainable UK headquarters for Fujifilm

£7.5m

Design and build scheme

A c. £7.5m headquarters led from first brief to handover.

30,000

Sq ft delivered

Showroom, workshop and offices over three storeys, with a Category A fit-out.

A

EPC rating

Built to BREEAM Very Good with an EPC A rating.

Delays to the utility connections, outside the building contract, affected the final programme and cost; the client was kept informed throughout. Images: mcs group. See our Project & Programme Management and Employer’s Agent services, or view all projects.