Case Study — Industrial & Logistics Jaguar Land Rover Soak & HVAC Facility, Coventry

Lead Cost Manager and Employer’s Agent from inception to handover on a £3m refurbishment and extension of an emissions testing facility for Jaguar Land Rover in Coventry.

The challenge

Upgrading a testing facility for JLR’s powertrain team

Industrial HVAC unit installed at high level

Jaguar Land Rover needed to adapt an existing emissions testing facility warehouse in Coventry to create new soak and HVAC test space for its powertrain division. The scheme combined refurbishment of the existing building with new build elements, creating new pits and office space.

Procured traditionally through a negotiated tender, the works were delivered within a 7-month construction programme, with careful control of cost and change at the interface between the existing building and the new construction.

Delivered by Ollie Thompson MRICS in a previous role at Mace.

Project facts

At a glance

Lead cost management and Employer’s Agent services from inception to handover, under a JCT Intermediate Building Contract with Contractor’s Designed Portion 2016.

Client

Jaguar Land Rover

Location

Coventry

Value

£3m

Our role

Lead Cost Manager and Employer’s Agent

Involvement

Inception to handover

Scope

Refurbishment and new build, with new pits and office space

Procurement

Traditional, via a negotiated tender

Contract

JCT Intermediate Building Contract with Contractor’s Designed Portion 2016

Programme

7-month construction programme

Our approach

Cost control from inception to handover

Pre-contract

Brief & Budget

Cost advice from inception set a realistic budget for adapting an existing, specialist testing building.

BriefBudgetRisk
Pre-contract

Cost Planning

Cost plans tracked the design for the refurbishment and new build elements, including the new pits and office space.

Cost planValueBenchmarking
Tender

Negotiated Tender

A negotiated tender with the contractor, testing rates and prices to secure value for JLR.

NegotiationPricingAward
Post-contract

Employer’s Agent

Administering the JCT Intermediate contract, including the Contractor’s Designed Portion, on JLR’s behalf.

AdministrationInstructionsNotices
Post-contract

Valuations & Reporting

Monthly valuations and cost reports kept JLR informed of cost and forecast outturn.

ValuationsReportingCash flow
Handover

Change & Handover

Change within the existing building was assessed for cost and time as it arose, with commercial close-out through to handover.

ChangeHandoverFinal account

The outcome

New test space for JLR’s powertrain division

£3m

Facility upgrade

Refurbishment and extension of an existing emissions testing facility for Jaguar Land Rover.

7

Month programme

Refurbishment and new build delivered within a 7-month construction programme.

JCT

Traditional route

JCT Intermediate with Contractor’s Designed Portion, procured through a negotiated tender.

See also our Jaguar Land Rover Vehicle & Special Operations Facility case study, or our Cost & Commercial Management services.

Start a Project

Tell us
about your scheme.

We’ll bring the programme, the governance and the certainty. Get in touch to discuss your project.