Case Study — Education Independent School Dining Hall, Bromsgrove

Quantity Surveyor and Employer’s Agent for the c. £3m refurbishment and extension of a dining hall at an independent school in Bromsgrove, from inception to RIBA Stage 3.

The challenge

A dated dining hall reworked for 1,400 pupils a day

Design visual of the dining hall extension with sedum roof

A leading independent school in Bromsgrove needed to modernise its dining hall. The existing building was inefficient, suffered from noise and cooking fumes, and looked dated alongside the rest of the historic campus.

The proposals refurbish the hall as a food-hall-style servery for 1,400 pupils a day, with new staff dining and a menu suited to the school’s international boarders. Three single-storey timber frame extensions, with brick, glass and stone facades and sedum roofs, complete the scheme. The cost plan and the JCT Design and Build route had to be set while the school kept running.

Delivered by Ollie Thompson MRICS in a previous role at Mace.

Project facts

At a glance

Appointed from RIBA Stage 0 through to Stage 3, with the scheme set up for a JCT Design and Build contract with client amendments.

Client

Independent school

Location

Bromsgrove, Worcestershire

Value

c. £3m

Contract

JCT Design and Build with client amendments

Our role

Quantity Surveyor and Employer’s Agent

RIBA stages

0–3, from inception to spatial coordination

Scheme

Dining hall refurbishment and three single-storey extensions

Construction

Timber frame with sedum roofs

Architect

Robothams

Our approach

From inception to contractor appointment

RIBA 0

Strategic Definition

Setting the brief, budget and programme for refurbishing and extending a dining hall that serves 1,400 pupils a day, with the school in operation.

BriefBudgetFeasibility
RIBA 1

Preparation & Brief

Working with the school and design team to define the servery, catering and staff dining requirements, and setting up cost reporting.

BriefCost PlanGovernance
RIBA 2

Concept Design

Costing the concept for the refurbishment and three single-storey extensions, and testing options against the budget.

DesignOptionsValue
RIBA 2

Cost & Value Review

Reviewing the timber frame, brick, glass and stone facades and sedum roofs for cost, buildability and value.

MaterialsValueRisk
RIBA 3

Spatial Coordination

Updating the cost plan as the design was coordinated and taken through planning.

PlanningCoordinationCost Control
RIBA 3

Procurement Strategy

Setting the JCT Design and Build route and drafting the client’s amendments, ready for the scheme to go to tender.

ProcurementAmendmentsRisk

The outcome

A modern food hall for a historic campus

£3m

Refurbishment & extension

Of an existing dining hall, costed from inception to RIBA Stage 3.

1,400

Pupils a day

A food-hall-style servery, plus new staff dining facilities.

3

New extensions

Single-storey timber frame extensions with sedum roofs to the north, east and south.

Images: Robothams. See also our Sidney Stringer Primary School case study, or our Cost & Commercial Management and Employer’s Agent services.