Case Study — Mixed Use One Eastside, Birmingham
Monitoring surveyor (fund monitor) for the bank lending to the developer, Court Collaboration, on a £200m, two-tower build-to-rent scheme of 667 homes, including a 51-storey tower that is one of the tallest in Birmingham.
The challenge
A £200m tower, independently monitored for the lender

One Eastside is a two-tower build-to-rent scheme in Birmingham’s Eastside, close to the new HS2 terminus at Curzon Street. Developed by Court Collaboration, it delivers 667 homes across a 51-storey tower and a 16-storey tower, with more than 23,000 sq ft of resident amenity space including a sky lounge, spa, gym, cinema, co-working space and landscaped gardens.
Lending on a tall building of this scale carries significant risk. The bank needed independent, expert assurance that the project was being delivered to programme, budget and quality, and that each drawdown reflected the value of work actually completed on site.
Delivered by Ollie Thompson MRICS in a previous role at Arcadis LLP.
Project facts
At a glance
Independent monitoring and reporting to the bank lending to the developer, through the construction of a 51-storey build-to-rent tower.
Client
Bank lending to the developer
Location
Eastside, Birmingham city centre
Value
£200m
Developer
Court Collaboration
Our role
Monitoring surveyor (fund monitor) for the lender
Height
51-storey and 16-storey towers
Homes
667 build-to-rent apartments
Amenities
23,000+ sq ft, including sky lounge, spa, gym, cinema and co-working
Project team
JRL Midgard (contractor), Glancy Nicholls Architects (design architect), Weedon Architects (delivery architect), Couch Perry Wilkes (building services)
Our approach
Independent assurance for the lender
Due Diligence
Review of the cost plan, programme, building contract and professional appointments, highlighting risks and conditions for the bank.
Budget Review
An independent check that the construction budget and contingency were realistic for a tall residential building of this scale.
Site Monitoring
Regular site visits to verify progress and quality against the programme and the contract.
Drawdown Certification
Each drawdown request was assessed against the value of work completed, so funds were released only for work in place.
Risk & Change
Variations, programme risks and claims were tracked and reported, giving the bank early sight of anything that could affect cost or completion.
Funder Reporting
Clear, regular reports gave the bank an independent view of cost, programme, quality and risk.
The outcome
667 homes on Birmingham’s skyline
667 new homes
One- and two-bedroom build-to-rent apartments, with a spa, gym, cinema, co-working space and a rooftop sky lounge.
A Birmingham landmark
The 51-storey tower is one of the tallest buildings in Birmingham and among the tallest build-to-rent towers in the UK outside London.
Lender confidence
Independent monitoring gave the bank assurance throughout the delivery of a £200m scheme.
Find out more about the role in our guide, What does a monitoring surveyor do?, or see our Monitoring Surveyor service. Developer? Use our free funding checklist.
Start a Project
Tell us
about your scheme.
We’ll bring the programme, the governance and the certainty. Get in touch to discuss your project.