Insights — NEC Contracts NEC Option A vs Option C: what’s the difference?

How the two most widely used NEC main options pay the contractor, who carries the cost risk, and how to choose between them.

Highway and infrastructure works under an NEC contract

In short: under NEC Option A the contractor is paid a fixed price for each completed activity and carries the risk of its own costs. Under Option C the contractor is paid its actual cost plus a fee, and any saving or overrun against an agreed target is shared with the client.

Both are main options of the NEC Engineering and Construction Contract (ECC), and both use an activity schedule that the contractor prices. The difference is what happens to that price once work starts.

Option A: priced contract with activity schedule

The contractor breaks the work into activities and prices each one. The total of those prices is the contract price. The contractor is paid for each activity when it is complete, whatever it actually cost to deliver.

  • Cost risk: sits mainly with the contractor. If an activity costs more than priced, the contractor absorbs it, unless the cause is a compensation event.
  • Price certainty: high for the client, provided the scope is well defined and change is controlled.
  • Administration: lighter. The Project Manager checks that activities are complete, not what they cost.
  • Change: compensation events are assessed on their forecast effect on cost and time, and added to the prices.

Option C: target contract with activity schedule

The activity schedule prices become a target. During the works the contractor is paid its actual Defined Cost plus its Fee, less any costs the contract disallows. At the end, the final cost is compared with the target, adjusted for compensation events, and the difference is shared between client and contractor in the proportions set in the contract (the pain/gain share).

  • Cost risk: shared. The client benefits from savings but also bears part of any overrun.
  • Price certainty: lower at the outset, but the target and share ranges give both parties a reason to keep costs down.
  • Administration: heavier. The contract is open-book, so the client’s team must check Defined Cost, timesheets, plant and subcontract costs, and identify Disallowed Cost.
  • Change: compensation events adjust the target rather than a fixed price.

Side by side

Option AOption C
Contractor is paidThe price of each completed activityDefined Cost plus Fee, then a share of any saving or overrun
Who carries cost riskMainly the contractorShared, through the pain/gain share
Best whenScope and design are well definedScope or risk is uncertain, or the contractor joins early
Client’s admin effortLowerHigher: open-book cost checking
Typical useBuildings and refurbishments with a settled designHighways, infrastructure and two-stage or early contractor involvement schemes

Which should you choose?

Choose Option A when the design is mature, the scope is unlikely to change and you want price certainty with a lighter administrative load. Choose Option C when there is real uncertainty in scope, ground conditions or interfaces, when the contractor is involved early to help develop the design, or when you want a collaborative, open-book relationship and have the resources to manage it.

A common pattern on infrastructure is a two-stage approach: the contractor develops the design and target under a first-stage appointment, then the works are let under Option C. Whichever option you use, the client’s amendments (the Z clauses) and the share ranges matter as much as the option itself, so they deserve careful drafting.

Frequently asked questions

What is NEC Option A?

Option A is a priced contract with activity schedule. The contractor prices each activity as a lump sum and is paid for completed activities. It carries the risk of its own costs being higher than its prices, and change is dealt with through compensation events.

What is NEC Option C?

Option C is a target contract with activity schedule. The contractor is paid its Defined Cost plus its fee, and any saving or overrun against the target is shared between the client and contractor using the agreed share ranges (often called pain/gain share).

Which option gives the client more price certainty?

Option A, because the client pays the agreed prices for completed activities. Option C gives less certainty on the final cost, but can suit work where the scope or risk is difficult to price fully at tender.

Is Option C more work to administer?

Yes. Because the contractor is paid Defined Cost, the client team needs to check and audit costs throughout the contract, so Option C needs more commercial resource than Option A.

Can Option C be used with a two-stage tender?

Yes. A common approach is a first-stage appointment where the contractor helps develop the design and the target, followed by an Option C contract for the main works.

How October Projects can help

We act as NEC Project Manager and commercial advisor under both options. Recent examples include the A38 Major Road Network, a two-stage scheme moving to Option C, and the Newbold Comyn and St Nicholas Park leisure centres, delivered under Option A with client amendments.

Based in the Midlands? Find out more about our project management services in Birmingham and our NEC and JCT contract administration.

Still deciding? Try our free Which contract is right for my project? tool. Answer five quick questions for a suggested JCT or NEC contract.

Working to an NEC4 deadline? Use our free NEC & JCT deadline calculator to work out compensation event, quotation and programme response dates.

Deciding on an NEC option? Get in touch, or read more about our contract administration and project management services.

← Back to news & insights

Work with us

Let’s talk about
your project.

Whatever stage your project is at, we bring senior expertise to manage programme, cost and quality from inception to handover.