Case Study — Industrial & Logistics Greenlight Redditch
Project Manager, Employer’s Agent and Quantity Surveyor for a c. £20m, 193,000 sq ft industrial and logistics scheme at Moons Moat, Redditch, targeting BREEAM Outstanding, from inception through to appointing the main contractor.
The challenge
Turning a former factory into a net zero ready estate

A logistics joint venture set out to redevelop a former manufacturing complex at Moons Moat in Redditch into a modern industrial and logistics estate: four new speculative units of 10,000 to 67,475 sq ft, with Category A offices, alongside the refurbishment and extension of an existing building for an occupier staying on site.
The sustainability targets were among the most demanding in the sector: BREEAM Outstanding, EPC A* and Net Zero Carbon in Operation Ready, with solar PV, air source heat pumps, rainwater harvesting and EV charging. All of this had to be set up and priced correctly before a contractor was appointed.
Delivered by Ollie Thompson MRICS in a previous role at Trinity Property Consultants.
Project facts
At a glance
Appointed from RIBA Stage 0 through to procuring the main contractor, on a JCT Design and Build contract with client amendments.
Client
Logistics joint venture
Location
Moons Moat, Redditch, Worcestershire
Value
c. £20m
Contract
JCT Design and Build with client amendments
Our role
Project Manager, Employer’s Agent and Quantity Surveyor
RIBA stages
0–4, from inception to contractor appointment
Scheme
193,000 sq ft: four new units and one refurbished and extended unit
Sustainability
BREEAM Outstanding, EPC A*, Net Zero Carbon in Operation Ready
Main contractor
Benniman
Our approach
From inception to contractor appointment
Strategic Definition
Setting the brief, budget and programme for redeveloping a live manufacturing site, including the units to be demolished, retained and extended.
Preparation & Team
Assembling the professional team and setting up project governance, reporting and cost control.
Concept Design
Testing the design against the cost plan and the BREEAM Outstanding, EPC A* and net zero targets.
Spatial Coordination
Coordinating the design and keeping the budget aligned as the scheme moved through planning.
Employer’s Requirements
Preparing the Employer’s Requirements and the client’s amendments to the JCT Design and Build contract.
Main Contractor Procurement
Running the tender, analysing the returns and appointing Benniman as main contractor.
The outcome
A sustainable estate, ready to build
Industrial scheme
193,000 sq ft of new and refurbished space.
Units
Four new-build units and one refurbished and extended unit.
EPC rating
With BREEAM Outstanding and Net Zero Carbon in Operation Ready.
Images: Trinity Property Consultants. See our Project & Programme Management and Employer’s Agent services, or view all projects.
Start a Project
Tell us
about your scheme.
We’ll bring the programme, the governance and the certainty. Get in touch to discuss your project.