Case Study — Sport & Leisure Newbold Comyn & St Nicholas Park Leisure Centres

Quantity Surveyor, with NEC project management support, for the £12.65m refurbishment and extension of two existing public leisure centres in Royal Leamington Spa, from RIBA Stage 0 to handover in 2018.

The challenge

Refurbishing and extending two live leisure centres

New fitness studio at Newbold Comyn Leisure Centre, Leamington Spa

A local authority client set out to transform two of its leisure centres in Royal Leamington Spa. At Newbold Comyn, that meant a two-storey extension that grew the footprint by 70%, a new sports hall, three fitness studios, a 100-station gym, a climbing wall and a biomass boiler, alongside a full pool and changing refurbishment. At St Nicholas Park, a new reception, café and gym, and a complete pool plant replacement.

The centres had to keep serving the public throughout: whenever one pool was closed, the other had to stay open. A high water table at Newbold Comyn meant the pool could not be fully drained, so its plant had to be replaced around it.

This was a refurbishment and extension project, not a new build. New pool plant, filtration, boilers and building services had to be designed and installed around existing mechanical and electrical systems that were still serving the buildings, with temporary plant keeping the centres running until the new systems could take over.

Delivered by Ollie Thompson MRICS in a previous role at Mace.

Project facts

At a glance

A refurbishment and extension of two occupied buildings, appointed from RIBA Stage 0 through to handover on an NEC Option A contract with client amendments.

Client

Local authority

Location

Royal Leamington Spa, Warwickshire

Value

£12.65m

Contract

NEC Option A with client amendments

Our role

Quantity Surveyor, with light-touch NEC project management (early warnings and compensation events)

RIBA stages

0–6, completed 2018

Newbold Comyn

Two-storey extension, sports hall, 100-station gym, 3 studios, pool refurbishment, biomass boiler

St Nicholas Park

New reception, café and gym, pool filtration and full plant replacement

Contractor

Speller Metcalfe

Our approach

Protecting cost and service across two live sites

RIBA 0–2

Cost Planning

Involved from the very start, with cost plans for both centres reflecting the risks of working with existing structures and services, giving the client a clear budget position as the design developed.

Cost PlanBudgetRisk
RIBA 3

Value Engineering

A further 10% value engineering saving was achieved at design stage, without losing the facilities the client wanted.

ValueSavingsSpecification
RIBA 4

Procurement

The contractor was appointed through a competitive tender and interview process, on an NEC Option A contract with client amendments.

TenderInterviewAppointment
RIBA 5

NEC Contract Management

Light-touch NEC project management support, managing early warnings and compensation events through the contract.

Early WarningsCompensation EventsProgramme
RIBA 5

Existing Buildings & Services

Works were carefully coordinated with the existing M&E, including temporary plant and a phased switchover, and sequenced so one pool always stayed open. Compensation events were assessed for cost and time.

Existing M&ETemporary PlantPhasing
RIBA 6

Handover

Both centres were completed in 2018 and handed back to the client.

CompletionHandoverFinal Account

The outcome

Two existing leisure centres, transformed

£12.65m

Refurbishment and extension

Two existing leisure centres extended and refurbished while both stayed open to the public.

10%

Value engineering saving

Achieved at design stage, on top of the competitive tender.

70%

Larger footprint

At Newbold Comyn, with a new sports hall, gym and studios.

Images: Speller Metcalfe. See our Cost & Commercial Management and Project & Programme Management services, or view all projects.

Start a Project

Tell us
about your scheme.

We’ll bring the programme, the governance and the certainty. Get in touch to discuss your project.