Case Study — RetailMeadowhall Shopping Centre Schemes, Sheffield

Lead cost management and Employer’s Agent services across a rolling programme of retail schemes at Meadowhall, from £50k unit refurbishments to £10m new retail space, delivered pre- and post-contract under JCT Design and Build.

The challenge

A rolling programme of retail works inside one of the UK’s largest shopping centres

Refurbished retail unit interior with new fit-out

On behalf of Meadowhall Limited Partnership and The British Land Company Plc, I acted as lead cost manager and Employer’s Agent on a series of projects within the Meadowhall shopping centre in Sheffield. Individual schemes ranged from around £50k to £10m.

The work covered the refurbishment of existing units, the conversion of space to new uses and the creation of new retail space. Each scheme was procured on a design and build basis under JCT Design and Build 2016 with the client’s amendments, using single-stage or two-stage tendering depending on the size and risk of the package.

Because the centre stayed open throughout, cost and contract advice had to account for trading hours, tenant handovers, landlord and tenant interfaces and tight access arrangements, while giving the client consistent reporting across a varied portfolio of live schemes.

Project facts

At a glance

Client: Meadowhall Limited Partnership / The British Land Company Plc
Location: Meadowhall, Sheffield
Value: £50k to £10m per scheme
Role: Lead Cost Manager and Employer’s Agent (pre- and post-contract)
Procurement: Design and build; single and two-stage tenders
Contract: JCT Design and Build 2016 with client amendments
Programme: Various

Cost planning

Order of cost estimates and elemental cost plans for each scheme, sized to the scope of works, from small unit refurbishments to major new retail space.

Procurement strategy

Advice on single-stage or two-stage tendering for each package, balancing price certainty, early contractor input and programme.

Employer’s Requirements

Preparing and coordinating the Employer’s Requirements and tender documents so contractor proposals could be compared on a like-for-like basis.

Contract amendments

Applying the client’s JCT Design and Build 2016 amendments consistently across schemes and advising on risk allocation.

Tender analysis

Tender returns analysed, clarified and normalised, with recommendations for award and value engineering where needed.

Employer’s Agent

Administering the D&B contracts post-contract: change, notices, payments, sectional and practical completion.

Valuations and change

Interim valuations, assessment of variations and early warning of cost movement against approved budgets.

Live centre interfaces

Accounting for trading hours, out-of-hours working, tenant handovers and landlord/tenant demarcation in cost and contract advice.

Final accounts

Agreeing final accounts promptly so the client had cost certainty and could close out each scheme within the wider programme.

Our approach

How each scheme was delivered

Brief

Brief and budget

Confirming the client’s objectives for each unit or space and setting a realistic budget.

BudgetBriefRisk
Design

Cost plan

Developing the cost plan alongside the design team as the scheme took shape.

Cost planDesignValue
Tender

Tender

Single or two-stage design and build tender, with Employer’s Requirements and amended JCT terms.

TenderERsJCT D&B
Award

Award

Tender analysis, negotiation and recommendation, then contract preparation.

AnalysisNegotiationContract
Construction

Construction

Employer’s Agent duties, valuations and change control while the centre kept trading.

ValuationsChangeReporting
Completion

Completion

Handover, final account agreement and close-out reporting.

HandoverFinal accountClose-out

The outcome

What this meant for the client

01

Consistency across a portfolio

One lead cost manager and Employer’s Agent across many schemes gave the client a consistent approach to budgets, contracts and reporting.

02

The right tender route

Single or two-stage tendering was chosen to suit each package, protecting price certainty without holding up the programme.

03

Cost certainty in a live centre

Change was controlled and final accounts agreed with the realities of a trading shopping centre built into the advice.

Delivered by Ollie Thompson MRICS in a previous role at Arcadis. Planning a retail refurbishment or fit-out? Talk to us about your scheme.