Lead Cost Manager and Employer’s Agent on pre-contract feasibility studies and options appraisals for a range of £5m to £30m regeneration schemes across Walsall, for the West Midlands Combined Authority.
The challenge
Feasibility and options for town centre regeneration

The West Midlands Combined Authority commissioned a series of feasibility studies and options appraisals for regeneration projects across Walsall, ranging from around £5m to £30m. These included the remodelling and enhancement of train stations and the conversion of retail units into residential homes.
Ollie provided pre-contract cost management and Employer’s Agent advice across the programme, helping the authority understand the cost, risk and deliverability of each option before committing to procurement. The schemes were planned for design and build delivery under JCT Design and Build 2016 with client amendments, through single or two-stage tenders, with construction programmes of 12 to 24 months.
Delivered by Ollie Thompson MRICS in a previous role at Mace.
Project facts
At a glance
Pre-contract cost management and Employer’s Agent services across a programme of feasibility studies and options appraisals in Walsall.
Client
West Midlands Combined Authority
Location
Walsall, West Midlands
Value
£5m to £30m per scheme
Our role
Lead Cost Manager and Employer’s Agent (pre-contract)
Scope
Station remodelling and enhancement, and retail-to-residential conversions
Services
Feasibility studies and options appraisals
Procurement
Design and build, via single and two-stage tenders
Contract
JCT Design and Build 2016, with client amendments
Programme
12 to 24-month construction programmes
Our approach
Pre-contract advice across a regeneration programme
Feasibility Studies
Testing the cost and deliverability of each scheme at the earliest stage, from station enhancements to retail conversions.
Options Appraisal
Comparing options on capital cost, risk and programme to help the authority choose the right schemes to take forward.
Cost Planning
Cost plans for the preferred options, aligned to funding and approval gateways.
Procurement Strategy
Advice on single-stage or two-stage design and build tendering to suit each scheme’s complexity and risk.
Contract Preparation
Preparing JCT Design and Build 2016 contracts with client amendments, alongside the Employer’s Requirements.
Employer’s Agent
Pre-contract Employer’s Agent advice, protecting the authority’s position ahead of contract award.
The outcome
Supporting regeneration across Walsall
Scheme values
A programme of regeneration schemes across Walsall ranging from around £5m to £30m.
Station enhancements
Remodelling and enhancement of train stations to improve the passenger experience.
Retail to residential
Converting redundant retail units into new homes to support town centre regeneration.
Planning a scheme of your own? Try our free Is my project ready to tender? checklist, or see our Strategic Advisory services.
Start a Project
Tell us
about your scheme.
We’ll bring the programme, the governance and the certainty. Get in touch to discuss your project.