Case Study — Mixed Use One Eastside, Birmingham

Monitoring surveyor (fund monitor) for the bank lending to the developer, Court Collaboration, on a £200m, two-tower build-to-rent scheme of 667 homes, including a 51-storey tower that is one of the tallest in Birmingham.

The challenge

A £200m tower, independently monitored for the lender

One Eastside, a 51-storey build-to-rent tower in Birmingham

One Eastside is a two-tower build-to-rent scheme in Birmingham’s Eastside, close to the new HS2 terminus at Curzon Street. Developed by Court Collaboration, it delivers 667 homes across a 51-storey tower and a 16-storey tower, with more than 23,000 sq ft of resident amenity space including a sky lounge, spa, gym, cinema, co-working space and landscaped gardens.

Lending on a tall building of this scale carries significant risk. The bank needed independent, expert assurance that the project was being delivered to programme, budget and quality, and that each drawdown reflected the value of work actually completed on site.

Delivered by Ollie Thompson MRICS in a previous role at Arcadis LLP.

Project facts

At a glance

Independent monitoring and reporting to the bank lending to the developer, through the construction of a 51-storey build-to-rent tower.

Client

Bank lending to the developer

Location

Eastside, Birmingham city centre

Value

£200m

Developer

Court Collaboration

Our role

Monitoring surveyor (fund monitor) for the lender

Height

51-storey and 16-storey towers

Homes

667 build-to-rent apartments

Amenities

23,000+ sq ft, including sky lounge, spa, gym, cinema and co-working

Project team

JRL Midgard (contractor), Glancy Nicholls Architects (design architect), Weedon Architects (delivery architect), Couch Perry Wilkes (building services)

Our approach

Independent assurance for the lender

Pre-funding

Due Diligence

Review of the cost plan, programme, building contract and professional appointments, highlighting risks and conditions for the bank.

Due diligenceAppointmentsContracts
Pre-funding

Budget Review

An independent check that the construction budget and contingency were realistic for a tall residential building of this scale.

BudgetProgrammeContingency
Construction

Site Monitoring

Regular site visits to verify progress and quality against the programme and the contract.

Site visitsProgressQuality
Construction

Drawdown Certification

Each drawdown request was assessed against the value of work completed, so funds were released only for work in place.

DrawdownsCertificationCost to complete
Construction

Risk & Change

Variations, programme risks and claims were tracked and reported, giving the bank early sight of anything that could affect cost or completion.

RiskChangeContingency
Construction

Funder Reporting

Clear, regular reports gave the bank an independent view of cost, programme, quality and risk.

Funder reportsLenderMonitoring

The outcome

667 homes on Birmingham’s skyline

667

667 new homes

One- and two-bedroom build-to-rent apartments, with a spa, gym, cinema, co-working space and a rooftop sky lounge.

51

A Birmingham landmark

The 51-storey tower is one of the tallest buildings in Birmingham and among the tallest build-to-rent towers in the UK outside London.

£200m

Lender confidence

Independent monitoring gave the bank assurance throughout the delivery of a £200m scheme.

Find out more about the role in our guide, What does a monitoring surveyor do?, or see our Monitoring Surveyor service. Developer? Use our free funding checklist.

Start a Project

Tell us
about your scheme.

We’ll bring the programme, the governance and the certainty. Get in touch to discuss your project.