Case Study — Infrastructure A38 Major Road Network

NEC Project Manager and Commercial Advisor to North Somerset Council on the A38 Major Road Network scheme, a two-stage contract with Octavius under an NEC Professional Services Contract, moving to NEC ECC Option C for construction.

The challenge

Nine improvements along a key regional corridor

Plan of the nine A38 Major Road Network scheme locations between Barrow Tanks and M5 Junction 22

North Somerset Council, working with Somerset Council and funded through the Department for Transport’s Major Road Network programme, is improving nine locations on the A38 between Barrow Tanks and the Edithmead Roundabout at M5 Junction 22. The aims are more reliable journeys, safer roads and better options for walking, cycling and public transport.

Five of the locations are in North Somerset: Barrow Lane to Dial Lane, West Lane to the Airport Terminal roundabout, the Airport Terminal to Silver Zone roundabouts at Bristol Airport, Langford, and Sidcot Lane to Hillyfields. The council appointed Octavius through the Gen-5 framework on a two-stage basis, with Stage 1 design under an NEC Professional Services Contract and construction to follow under NEC ECC Option C.

Delivered by Ollie Thompson MRICS in a previous role at Rider Levett Bucknall.

Project facts

At a glance

Appointed as NEC Project Manager and Commercial Advisor across a two-stage contract: an NEC Professional Services Contract for Stage 1, with construction to follow under NEC ECC Option C.

Client

North Somerset Council

Location

A38 corridor, North Somerset

Funding

Department for Transport Major Road Network programme

Contract

NEC PSC (Stage 1), then NEC ECC Option C

Our role

NEC Project Manager and Commercial Advisor

Procurement

Two-stage, via the Gen-5 Civil Engineering, Highways and Transportation framework

Scheme

Five junction and corridor improvements, part of a nine-location scheme

Objectives

Journey reliability, road safety and active travel

Main contractor

Octavius

Our approach

From inception to contractor appointment

Stage 1

Two-Stage Procurement

Supporting the council through two-stage procurement on the Gen-5 framework and setting up the contractor’s Stage 1 commission under the NEC Professional Services Contract.

Gen-5PSCTwo-Stage
Stage 1

NEC Contract Management

Acting as NEC Project Manager on the PSC, managing early warnings, compensation events, programme submissions and payments.

Early WarningsCEsProgramme
Stage 1

Design Development

Managing the contractor’s detailed design across five locations and coordinating it with the council’s highways, design and stakeholder teams.

DesignStakeholdersCoordination
Stage 1

Commercial Advice

Advising the council on cost, risk and scope, and reviewing the contractor’s pricing as the target cost for construction was developed.

Target CostRiskValue
Stage 2

Main Contract Preparation

Preparing for construction under NEC ECC Option C, a target cost contract with an activity schedule and shared pain/gain.

Option CScopePain/Gain
Stage 2

Construction Readiness

Setting up the reporting, change control and cost management needed to run the construction phase under Option C.

ReportingChange ControlCost Control

The outcome

A two-stage route to a target cost

9

Locations

On the A38 from Barrow Tanks to M5 Junction 22, five of them in North Somerset.

2

Stage contract

Design under the NEC PSC, with construction under NEC ECC Option C.

DfT

Funded

Through the Department for Transport’s Major Road Network programme.

Images: North Somerset Council. See our Project & Programme Management, Contract Administration and Cost & Commercial Management services.